Lake Merced Raise Water Level Assessment
Project Schedule
The SFPUC has specified in the RFP that it desires to have a project that can be presented to the Commission in early autumn 2002. Using this goal, we have worked back through the schedule as follows.
As noted previously, the autumn decision-making schedule requirement can be met only if the phase 1 project qualifies for a CEQA categorical exemption or a mitigated Negative Declaration (MND). In the case of a MND, there is a minimum 30-day public review period on the Draft MND. Given this restriction, the following approximate schedule of key milestones for Phase 1 is proposed assuming the requirement for preparing a MND. If a categorical exemption can be obtained, then the schedule for the evaluations could be expanded within the available time frame and the action taken by the Commission moved forward to early October. Note that refinement of the schedule will occur during the Task 1 Work Plan development.
PHASE 1
Notice to Proceed August 1, 2002
Project Start-up Meeting August 5
Submit Draft Work Plan (Task 1) August 8
Belt Transect Surveys (Task 2) August 12 – August 30
SFPUC Staff Review Comments on Work Plan to EDAW August 12
Submit Final Work Plan August 14
Submit Data Gaps Report (Task 1.4) August 15
Submit Task 2 Technical Memo (Draft) August 20
SFPUC Staff Comments to EDAW on Task 2 Tech Memo August 22
Submit Task 2 Final Technical Memo August 26
Submit Task 3 Draft GIS Overlays + Technical Memo August 26
SFPUC Staff Comments on Task 3 GIS + Tech Memo to EDAW August 28
Task 4 Environmental Impact Assessment August 26 - September 5
Submit Task 3 Final GIS + Technical Memo September 4
Submit Task 5 Draft Technical Memo + Task 7 Admin Draft MND September 13
SFPUC Staff Comments to EDAW on Task 5 Tech Memo September 16
SFPUC Staff Comments to EDAW on Administrative Draft MND September 17
Submit Task 6 In-Field Monitoring Technical Memo September 20
Submit Task 5 Final Technical Memo + Draft MND September 20
NOI and Draft Report and Draft MND Published September 23
30-day Public Review September 23 – Oct. 23
Response to Comments and Staff Report October 25
Commission Hearing on Phase 1 Project October. 29
Task 10 Submit Implementation Schedule 1 November 1, 2002
PHASE 2
Submit Draft Work Plan (Task 1) November 5, 2002
SFPUC Staff Review Comments on Work Plan to EDAW November 7
Submit Final Work Plan November 12
Task 2 Review and Analysis of Operational, Environmental and
Regulatory Issues November 7, 2002 – March 17, 2003
Submit (Draft) Task 2 Technical Memorandum March 31, 2003
SFPUC Staff Review Comments on Task 2 Tech Memo to EDAW April 16
Submit Final Task 2 Tech Memo May 6
Presentation to Commission May 20, 2003