Response to December 18, 2003 RWQCB
comments on Preliminary Water Quality Screening Plan -
Lake Merced Stormwater Enhancement
Project
January
12, 2004
North
San Mateo
County Sanitation District (NSMCSD), a subsidiary of the City of Daly
City, and
the San Francisco Public Utilities Commission (SFPUC) are working to
address a
number of integrated resource management issues associated with
improving water
levels at Lake Merced. A Memorandum of
Understanding between the parties dated November 26, 2001 established a
work
effort to assess the reintroduction of stormwater from the Vista Grande
drainage basin back into Lake Merced as a source of lake recharge. A proposed Supplemental Environmental
Project (SEP) (NSMCSD 2003) would expand upon NSMCSD’s efforts to
evaluate the
feasibility of using diverted Vista Grande stormwater as a means to
increase
source water to Lake Merced. The
ultimate goals include implementing Best Management Practices (BMPs) to
treat
stormwater, increasing the water level of the lake and potentially
alleviating
flood control problems associated with peak stormwater flows adjacent
to South
Lake Merced.
On
December 8, 2003 the NSMCSD and SFPUC
transmitted a Preliminary Water Quality Screening Plan, 2003/04 Wet
Season for
the Lake Merced Restoration - Phase 2 Pilot Stormwater Enhancement
Project
(Plan) dated December 2003 to the SF Bay Regional Water Quality Control
Board
(RWQCB) other interested parties for comments.
RWQCB transmitted comments on the Plan to the NSMCSD and SFPUC
on
December 18, 2003. Responses to the RWQCB’s December 18, 2003 comments
are
included below.
In
addition, this document includes a
response to RWQCB comments on NSMCSD’s Supplemental
Environmental Project (See Appendix A).
Concurrently,
the Plan was peer reviewed by
Dr. Robert Cooper, Emeritus Professor of Pubic Health at the Univ. of
CA,
Berkeley. Dr. Cooper’s comments are
dated December 26, 2003 and are
attached to this response. Dr. Cooper states, "The methods in the plan
appear appropriate to give a preliminary indication of whether there
would be a
water quality impact due to the pilot diversion." He also notes
the
results will be used in the development of a strategy to "scale up"
the pilot diversion and design of a future associated
monitoring
program. Perhaps his review is best summed up by Dr. Cooper when
he
states: "Introduction of Vista Grande stormwater to Lake Merced
requires consideration of the tradeoff between the potential
environmental
benefits of adding additional water to the lake and the potential risks
such as
human health impacts. The pilot study appears to be an
appropriate first
step in gathering information required to make an informed
decision
regarding the balancing of these two potential conflicting
priorities."
Existing and Potential Beneficial Uses of Lake Merced: While the RWQCB’s Basin Plan lists both Water Contact Recreation and Non-Contact Recreation as existing uses, it is important to understand that swimming has been prohibited at Lake Merced since at least 1950 by SFPUC Resolution and practice. Fishing and boating are the only two potential water contact activities allowed at Lake Merced pursuant to SFPUC and SF Recreation and Park Department requirements. The SF Health Department supports the prohibition of body contact recreation at Lake Merced. Therefore, the bacteriological criteria applicable to body contact recreation utilized for this pilot project (CCR Title 17, Article 4, 7958 and RWQCB Basin Plan) is highly conservative and provides a significant factor of safety.
Lake Merced is designated by the RWQCB as a potential source of drinking water and by the SFPUC as an emergency drinking water source. However, it has not been used as such since the 1930’s and does not meet drinking water standards. In the unlikely event that the lake is ever needed for an emergency water supply, the SFPUC would issue a “boil water” order.
RESPONSE
TO RWQCB COMMENTS
1) Comment: The proposed Plan appears to be generally
directed at the
human health threats of coliform
and does not
adequately address other priority
stormwater
pollutants of concern appropriate in a baseline study
of this nature. Along with the proposed sampling analysis parameters, the following additional priority
stormwater
pollutants of
concern should be included in the Plan: Petroleum hydrocarbons (normally
EPA 8015 and/or 8020), 17 priority metals
(CAM 17);
Fecal coliform; and a limited
screening for candidate
pesticides/herbicides. Lastly, we strongly
recommend use of ammonia and nitrate field kits which can indicate high coliform levels and provide
immediate
results.
Response: The monitoring parameters
selected in the
Plan were based on a review of Vista Grande Stormwater data from 8
representative storms sampled during the 2002/2003 winter (CH2MHill,
2004) and
an analysis of stormwater data by EDAW (Aug. 2003) which indicates that
bacteria and nutrients are the primary pollutants of concern relative
to the
discharge of stormwater from the Vista Grande Canal into Lake Merced
and
protection of beneficial uses. The Plan
was thus designed to monitor the primary pollutants requiring treatment
(i.e.,
bacteria and nutrients). In addition,
the Plan included analysis of the five most common metals detected in
typical
municipal stormwater (Cr, Cu, Ni, Pb, and Zn), as well as Total
Dissolved
Solids, Total Suspended Solids, alkalinity and hardness.
These
monitoring results are summarized in a January 2004 report
titled: Phase 1 Vista Grande Stormwater Monitoring Program prepared by
CH2MHill. We understand that the CH2MHill data was not provided in the
original
submittal and thus Regional Board staff was not fully aware of the
extent of
the previous 2002/2003 monitoring program.
The SFPUC has previously submitted the EDAW (Aug. 2003) report
to
Regional Board staff.
A summary of the Vista Grande Stormwater Canal 2002/2003 Phase 1
monitoring results and specific responses to RWQCB recommendations are
included
below:
Pesticides and Herbicides: Stormwater
was sampled during 5
of the 8 storms using EPA methods 8151 and 8140 Organophosphorous
Pesticides
and Chlorinated Herbicides. None of the analytes were detected above
the method
detection limit in any of the ten samples. Therefore, additional
sampling for
pesticides and herbicides does not appear warranted.
Total
Petroleum Hydrocarbons: Stormwater
was sampled during all 8 storms using EPA methods 8015.
Of 16 samples collected, only two had levels above 1.0 mg/l (one
each at 2.6 and 1.5 mg/L). Given that USEPA’s Stormwater Benchmark for
Oil and Grease is 15 mg/l, we believe that additional sampling for TPH
is not warranted at this time. The benchmarks are the pollutant
concentrations above which EPA determined represents a level of
concern. The level of concern is a concentration at which a storm water
discharge could potentially impair, or contribute to impairing water
quality or affect human health from ingestion of water or fish. The
benchmarks are also viewed by EPA as a level, that if below, a facility
represents little potential for water quality concern. (See page17031 at:
http://www.epa.gov/fedrgstr/EPA-WATER/2000/March/Day-30/w7203.htm)
Metals: Stormwater
was sampled during all 8 storms for Ag, Cd, Cr, Cu, Ni, Pb, and Zn.
This list
includes all of the metals included on USEPA’s list of Stormwater
benchmarks
except Fe and Al. Based on the results
of the 2002/2003 sampling, silver and cadmium were not detected. The
Plan does
call for monitoring the five most common metals detected in typical
municipal
stormwater (Cr, Cu, Ni, Pb, and Zn), as well as Total Dissolved Solids,
Total
Suspended Solids, alkalinity and hardness.
We do not believe that the CAM 17 metals is an appropriate list
to use
to characterize stormwater quality. Rather, the list of CAM 17 metals
(22CCR,
Section 66261.24(a)), is a list developed to determine if a waste is
hazardous
in California. Based on the above
information, the monitoring of Cr, Cu, Ni, Pb, and Zn, as included in
the December
2003 Plan, is sufficient and the addition of other metals is not
warranted at
this time.
Total
Coliform: The December 2003 Plan calls for monitoring 3 bacteria
indicators: Total coliform, E coli, and Enterococci.
RWQCB staff has requested that fecal coliform be added. We do
not
believe that monitoring for fecal coliform is warranted for several
reasons:
Regulatory authorities allow for the replacement of fecal with E. coli. The State Water Resources Control Board is
working with counties up and down the state for coastal monitoring and
has
approved of counties using E. coli as a surrogate for fecal coliform. EPA, Region IX’s water quality group has
approved the use of E. coli as a surrogate for fecal coliform. The San Francisco Bay Regional Water Quality
Control Board’s NPDES Division has
approved the use of E. coli as a replacement for fecal coliform in San
Francisco’s Bayside NPDES permit. The
Quanti-Tray method of analysis, which is used extensively in California
coastal
monitoring programs for total and E. coli, does not provide a result
for fecal
coliform. Lastly, the Peer Review by Dr.
Robert Cooper, Emeritus Professor of Pubic Health at the Univ. of CA,
Berkeley
dated December 26, 2003 indicates that fecal coliform analysis is not
necessary
for the Pilot Screening Program.
Use of ammonia and nitrate
field
kits: We are currently researching
this suggestion and would like to discuss the RWQCB’s experience in
using ammonia and nitrate field kits
for providing an
indication of high coliform levels
at our
January 15, 2004 Meeting.
In
summary, the
monitoring program for the pilot program would include the following
analytes,
methods and reporting limits:
Analyte
|
Analysis Method |
Reporting Limit |
|
Cr, Total |
EPA 200.7 |
10.0 ug/L |
|
Cu, Total |
EPA 200.7 |
10.0 ug/L |
|
Ni, Total |
EPA 200.7 |
10.0 ug/L |
|
Pb, Total |
EPA 200.7 |
3.0 ug/L |
|
Zn, Total |
EPA 200.7 |
20.0 ug/L |
|
Alkalinity |
EPA 310.1 |
20 mg/L |
|
Hardness |
EPA 130.2 |
2.0 mg/L |
|
Total Dissolved Solids |
EPA 160.1 |
10 mg/L |
|
Total Suspended Solids |
EPA 160.2 |
10 mg/L |
|
Orthophosphate |
SM 4500-P A,B,C |
0.060 mg/L |
|
Phosphorus, Total |
SM 4500-P A,B,C |
0.2 mg/L |
|
Ammonia |
SM 4500-NH3 C,E,N |
0.7 mg/L |
|
Total Kjeldahl Nitrogen |
SM4500-N B |
0.6 mg/L |
|
Nitrate |
SM4500-NO3B B |
0.20 mg/L |
|
Nitrite |
SM4500-NO2B B |
0.20 mg/L |
|
Total Coliform & E.Coli |
SM 18 9221B&E* |
10 – 24,190 MPN/100 ml |
|
Enterococci |
EPA 1600 |
10 – 24,190 MPN/100 ml |
*Modified
with MUG
for E. Coli
2)
Comment: The proposed Plan
does not have adequate sampling station locations to monitor the priority stormwater pollutants of
concern
appropriate in a baseline study of
this
nature. At a minimum, monitoring locations should be located: a) Before entering the
Continuous Deflection
System (CDS)
unit; b) After leaving
the CDS unit; c) In Soil and water samples
in the wetland treatment area; d) LM-1; e) LM-2; f) LM-3 and, g)
LM-PR.
Sampling should also be performed at different lake water levels, not
just at the surface, to evaluate pollutant
stratification
in the Lake water.
Board staff
feels that the additional monitoring
locations are
important in gathering appropriate and
meaningful
information about the overall fate
and
transport of stormwater pollutants in the Lake.
Additionally, Regional Board staff strongly support the use of dye test
studies to calibrate detention times and
identify optimum
sampling locations, however we find
insufficient details in the Plan. Please discuss
the proposed dye test in a more detailed and strategic manner (dye type, application rates/locations,
sampling, etc.).
Response: Several additional monitoring
stations will
be added. However, please note that the intent of the Plan is to
provide
preliminary screening information to determine if future, more
detailed,
evaluation is warranted. The intent of the Plan is not to provide an
exhaustive
analysis of all aspects of the pilot wetland treatment system. Has the Regional Board required such
sampling for other discharges of municipal stormwater to surface water
bodies
in the San Francisco Bay Area?
Additional
monitoring stations: Additional stations
will be added as requested with the exception of
the sample station prior to entering the CDS Unit and soil sampling in
the
wetland. The monitoring results from
the 2002/2003 show that the CDS does not significantly affect the level
of
bacteria and nutrients that are the focus of the Plan (CH2MHill, 2004). We will also supplement in-lake sample
stations LM-1, 2, 3 and LM-PR with three additional sample stations to
better
monitor the lateral extent of discharges to Lake Merced.
Given the limited duration of the test we do
not believe that collecting and analyzing soil samples in the wetlands
will
provide meaningful results.
Vertical
Sampling:
Vertical sampling does not appear warranted at this time. Lake Merced
is a
shallow lake (generally less than 20 feet deep) and experiences primarily isothermal conditions
with infrequent, weak stratification based on bimonthly ambient multi
level
monitoring data collected by the SFPUC (EDAW, Aug. 2003).
During the summer there is a slight period
of stratification evident in some profiles, but it is not sufficiently
strong
to impede mixing on a seasonal basis for current lake elevations. During the winter, the lake does not
typically
stratify at all. Water depth immediately offshore of the treatment
wetlands is
generally less than 15 feet.
Bacteriological and nutrient loading concerns, which are the
focus of
this project, will be adequately addressed based on the surface samples
proposed in the Plan. We do not believe
that vertical sampling is warranted for this preliminary water quality
screening plan.
Dye test: A dye test
was conducted on December 22, 2003. Additional information
concerning
the Dye test is included in Appendix B.
The intention of the dye test was to identify any noticeable
short-circuiting of water flows in the system and to approximate mixing
and
retention times for the pilot test. Water was pumped from Lake Merced
using
portable pumps and discharged into the upstream end of the 300 ft long
perforated
pipe to approximate a storm discharge. The weather was clear and it had
not
rained for the past 24 hours. Total
flow was approximately 570,000 to 608,000 gallons based on the flow
rate of
3000 to 3200 gpm over a time period of 3 hrs.15 min. The amount of dye
injected
was sufficient for a strong visual observation at 1 ppm for 126,000
gallons to
a weak visual of 100 ppb for 1.26 million gallons. SFPUC
biologists
monitored the shoreline from a boat in the open water near the
shoreline beyond
the tule growth that occurs along the lake edge. No
dye was observed in the open water during the 3 hr and 15 min
test based on a flow rate of 3000-3200 gpm.
3) Comment: During sampling,
visual observations should also be noted for changes
in appropriate wildlife conditions (particularly the number and type of flora and fauna) and other general
conditions
(e.g., weather, floating trash,
water levels,
recreational use, etc.). In
addition, it would be an opportunity to
conduct and
maintain a photographic history of
changes in
key areas of the Lake.
Response: The suggested additions to the
visual
monitoring will be included in the revised Plan.
4) Comment: The Plan does not
contain adequate information regarding the Vista Grande Stormwater diversion volume flow rate
limits and associated
safeguards to cease and desist a diversion,
should
environmental or human health water
quality
threats occur. For example, should significant
surface runoff occur over the
wetland
treatment area, or,
if high pollutant concentrations are found in the Lake, there should be
a clear strategy and associated procedures so that the stormwater diversion
discharge will be immediately shut off.
Please describe this section in more detail and include an evaluation
of the wetland areas bio-retention capacity
and
effectiveness. This evaluation
should
describe flow attenuation as well
as pollutant
removal. Specific flow rate limits
should also
be discussed and appropriate
adaptive
management safeguards that will be in place to
prevent water quality threats. The Plan should clearly describe
what
would be considered an environmental or
human health
threat (i.e., coliform exceeds DHS
limits, or
other parameters exceed Basin Plan limits,
etc.).
Response: The Phase
2 pilot project will be approached in
stages,
starting with small releases of Vista Grande water and increasing the
size of
those releases only after monitoring the effects of earlier releases. We will have the ability to regulate and
continuously
measure the flow into Lake Merced up to a maximum flow rate of about
4000 gpm. We plan to start at a lower flow
rate of 500
gpm with the first storm and collect samples. If the levels are
acceptable,
then we can increase the flow rate during subsequent storms. This will
give us
an opportunity to judge the treatment effectiveness relative to flow
rate.
The flow rate
and duration of pilot discharges are listed in Table 2,
below. Samples will be collected at onshore and in the wetlands during
the
storm. For safety reasons and to allow sufficient time for stormwater
to mix
with lake water, off shore samples will be collected within 24-48 hours
following discharge. If pollutant concentrations are found to exceed
the levels
listed in Table 3, the discharge rate of the subsequent test will be
reduced or
the test will be discontinued. The total volume in South Lake as of
December 1,
2004 is approximately 925,000,000 gallons. The individual pilot
discharges
would range from about 0.1 to 1% of the total lake volume in South Lake.
Vista Grande Stormwater Phase 2 Discharge Rate and Duration
|
Storm No. |
Flow Rate |
Duration |
Volume2 |
|
1 |
500 gpm |
24 hours |
720,000 |
|
2 |
500 gpm |
48 hours |
1,400,000 |
|
3 |
1500 gpm |
24 hours |
2,160,000 |
|
4 |
1500 gpm |
48 hours |
4,320,000 |
|
5 |
3000 gpm |
48 hours |
8,640,000 |
|
6 |
Background Storm1 |
|
|
1One
storm will be monitored to access lake water
quality in the absence of diversion of Vista Grande Stormwater.
2Volume
assumes that flow rate can be maintained for
entire duration period.
Target and Maximum Levels for Phase 2 Pilot
Stormwater Treatment Project
|
Constituent |
Target Level in Lake Merced (MPN/100mL) |
Basis |
Levels that are not to be exceeded (MPN/100mL) |
Basis |
|
Total coliform |
1000-6000 |
General historic range of ambient Lake Merced
total coliform levels |
10,000 |
CA DHS and RWQCB maximum standard |
|
E coli |
<126 |
SFPUC criteria for issuing a health advisory
for swimming beaches1 |
400 |
Lower of CA DHS
and RWQCB maximum standards |
|
Enterococci |
<35 |
SFPUC criteria for issuing a health advisory
for swimming beaches1 |
104 |
Lower of CA DHS
and RWQCB maximum standards |
|
NH3 |
0.05 |
Background levels in Lake Merced (South Lake) |
None required for pilot test. |
Nutrient additions will not cause human
health or ecological concerns from short term pilot tests |
|
TKN |
3.86 |
|||
|
PO4 |
0.06 |
|||
|
TP-P |
0.16 |
Notes: DHS:
CCR Title 17, Article 4, 7958
RWQCB: Basin Plan
1Swimming
in Lake Merced is prohibited.
Regional Board staff has
asked for
an evaluation of the
wetland areas bio-retention capacity and effectiveness. The primary objective of the Phase 2 pilot
test is specifically to provide such an estimate of the effectiveness
of the
existing natural wetland. Literature data for coliform die off rates
and
nutrient uptake are highly variable. The dye test conducted on December
22,
2003 (See Response to Comment 2) indicated that there was no obvious
short-circuiting during the 3 hr and 15 min test based on a flow rate
of
3000-3200 gpm and a total flow of
approximately 570,000 to 608,000 gallons.
By performing a real pilot test, actual data on the treatment capability can be obtained by leveraging the existing infrastructure (the CDS unit and a pipeline under John Muir Road).
Again, the Plan calls
for starting with a low flow rate and
ramping up to find the maximum rate where treatment is effective. If the Phase 2 program provides positive
results, then additional, more detailed modeling and analysis will be
conducted
as part of evaluating building a larger constructed wetland and/or
using a
larger natural wetland area. The pilot project is
a positive step in adding a
local watershed source of water to Lake Merced using a “treatment
train”
approach. Ultimately, additional
treatment may still be necessary.
5) Comment: Lastly, we request additional
efforts by Daly City and the
San Mateo
County Stormwater Program to further investigate priority stormwater
pollutant source areas and to minimize
runoff to the Vista
Grande Canal to the maximum extent
practicable.
Response: The City of Daly City is a co-permittee agency of the San Mateo Countywide Stormwater Pollution Prevention Program. The City has been involved since the inception of the program in 1993. As such, Daly City is responsible for compliance with NPDES stormwater best management practices associated with all municipal specific program requirements aimed at the prevention of pollutants to enter stormwater.
Since January 2001, as part of a cooperative effort with the San Francisco Public Utilities Commission to raise water levels at Lake Merced, Daly City has been examining the issue associated with coliform in the stormwater being discharged in the Vista Grande Drainage Basin. Daly City’s interest is to examine the re-introduction of stormwater within the Vista Grande Drainage Basin watershed back into Lake Merced as a sustainable source of water to maintain lake levels. To date, Daly City has spent over $403,000 toward finding and addressing the source of coliform within the Vista Grande Drainage Basin, and as yet, a “smoking gun” source has yet to emerge.
Efforts to date include:
· Bioassay of canal water using trout produced inconsistent results.
· Sampling begun in May 2001 note both total and fecal coliform present.
· Begin DNA fingerprinting in September 2002 noting presence of animal and human DNA.
· Smoke Testing of 31 miles of Vista Grande Drainage Basin conducted in Spring of 2002. Nine cross connection problems identified and all problems corrected.
· Installed two Continuous Deflection System (CDS) Units in Fall 2002, units became operational in December 2002 with eight storm events tested and analyzed.
· Developed a response plan to address 113 chronic sewer lateral (identified as three or more call outs absent corrective action). Notice to Repair sent out in April 2003. To date, 93 home repairs have been verified, 3 are under permit, 8 in permit process and 9 enforcement actions pending.
· Conducted a Sewer System Evaluation Survey to conduct dye testing of homes within the 24-inch sub basin of the Vista Grande Drainage Basin in July 2003. Purpose was to systematically identify if sewer cross connections existed in the basin. Basin divided into seven zones downstream to upstream home dye test sequence and retrieval of cotton test pads. 950 homes testing accounting for 92 storm drain manholes. Two cotton pads retrieved positive for dye. Some 2,562 feet of pipe video inspected yet no cross connection was found.
References:
EDAW,
Inc., August
2003, Task 3 Technical Memorandum:
Lake Setting, Alternative Lake
Levels and Supplemental Water Requirements, Supplemental Water Sources,
Lakeside Vegetation (Draft).http://sfwater.org/detail.cfm/MSC_ID/60/MTO_ID/55/MC_ID/7/C_ID/1618/holdSession/1
Appendix
A:VISTA
GRANDE PILOT PROJECT SEP CRITERIA
Section A.
Basis
and Purpose
The North San Mateo County Sanitation District, a subsidiary of the City of Daly City, appreciates the Regional Board’s encouragement of the submittal of Supplemental Environmental Project (SEP) in lieu of a portion of an imposed ACL. The SEP proposed by the NSMCSD complies with the integrity of an SEP scope of work consistent with an ACL liability calculated by Regional Board staff in the amount of $30,180. The NSMCSD also appreciates that the Regional Board does not select projects but rather allows a Discharger to identify a project it would like to fund in furtherance of an identified community interest. The SEP identified by the NSMCSD proposes reasoned, rational and appropriate preliminary pilot project focused to help determine if the introduction of stormwater to Lake Merced will impact the lake’s beneficial uses. The SEP is supported by the San Francisco Public Utilities Commission (SFPUC) and California Trout, the lead public interest group that has filed a claim with the State Water Resources Control Board that named Daly City as a co-defendant.
General SEP Qualification Criteria
|
(A) Measures that go beyond all legal obligations of the Discharger.
The NSMCSD does not have any legal obligation associated with Lake Merced as it is an asset of the SFPUC. As owner of Lake Merced, the SFPUC is agreeable to working with the NSMCSD in accomplishing the pilot study as an appropriate first step toward the examination of the use of stormwater discharge, one of four source water alternatives being examined as part of comprehensive review on how to improve and sustain water levels at Lake Merced. The NSMCSD is not under any other regulatory obligation associated with stormwater discharge save that associated with its participation as a co-permittee agency under the San Mateo Countywide Stormwater Pollution Prevention Program that incorporates best management practices.
The SEP provides an opportunity, as part of NSMCSD ongoing voluntary cooperation with the SFPUC, to accelerate an examination into the re-introduction of stormwater generated throughout Daly City as a source water into the lake. Presently, stormwater flows are directed away from the lake and discharged onto the beach beneath Fort Funston. During heavy rainfall events, stormwater from Vista Grande Canal has overflowed onto John Muir Drive and into Lake Merced. Thus, overflows have caused flooding problems and roadway/pathway destruction along Lake Merced. Diversion of stormwater could potentially provide dual benefits of flooding protection and a sustainable source of lake recharge.
(B) The SEP should benefit or study surface water quality and quantity, and the beneficial uses of waters of the State.
Of the four subjects offered, Environmental Restoration, described as projects that either restore or create natural environments, best characterizes the purpose of the SEP. The SEP intends to provide a pilot study level of analysis of stormwater quality that expands upon evaluating the feasibility of using Continuous Deflection Units to treat stormwater as a means to increase source water into Lake Merced that is part of an ultimate goal of increasing and sustaining water level of the lake. The pilot project represents an appropriate next phased study approach to stormwater testing performed during the 2002-03 rainy season during which stormwater was diverted, treated through two CDS units, tested and pumped back into the Vista Grande Canal. The SEP intends to examine baseline lake water quality and, upon regulatory approval, open an existing gate valve at the headworks of the Vista Grande Tunnel. A limited flow of stormwater would enter the CDS units and be directed into an existing overflow structure that crosses beneath John Muir Drive to a newly installed 300-foot perforated 12-inch HDPE pipe installed along a vegetated bank at Lake Merced. The pilot testing at limited flows is patterned after BMP guidance TC-10 (Infiltration Trenches) and TC-21 (Treatment Wetland). It is expected that the infiltration trench and existing natural wetland will assist with the removal of total suspended solids, biochemical oxygen demand, nutrients and possibly bacterial organisms before reaching the lake’s open water. As testing results are assessed, stormwater that flows through the CDS units can be increased as storm events permit or the gate valve closed. The following factors, both qualitative and quantitative, will be used to judge the project’s overall effectiveness: Lake Water Level, Receiving Water Quality, CDS and Infiltration/Vegetation Treatment, Flood Frequency and Vegetation Coverage.
Further, an SEP should be located near the Discharger, in the same watershed. The Vista Grande Stormwater Pilot Project at Lake Merced is approximately one mile away from the NSMCSD Treatment Plant and is in the watershed that could be used to help sustain lake levels.
2. Location is Vista Grande Drainage Basin in Daly City and Lake Merced in San Francisco.
3. SEP dated September 8, 2003 previously submitted. Preliminary Water Quality Screening Plan 2003-04 Wet Season dated December 4, 2003 sent to staff.
Reporting dates acknowledged upon Executive Officer approval.
Requirements acknowledged.
SEP Budget contains requisite 6% for SEP project oversight to be performed by Dr. Robert C. Cooper, Professor Emeritus of the School of Public Health, University of California at Berkeley. Dr. Cooper was chosen as the NSMCSD would be hard-pressed to find another individual possessing Dr. Cooper’s credentials to assess potential public health impacts.
Appendix B
Summary of Dye Test Performed Dec. 22, 2003
Lake Merced Pilot Wetland Treatment Study
On the morning of Dec. 22, 2003, the SFPUC and City of Daly City performed an initial flow characterization study of a proposed wetland treatment area on a vegetated area in proximity to the newly installed Continuous Deflection System (CDS) device as a storm water treatment structure. The intention of the dye test was to identify any noticeable short-circuiting of water flows in the system and to approximate mixing and retention times for the pilot test. Water was pumped from Lake Merced using portable pumps and discharged into the upstream end of the 300 ft long perforated pipe to approximate a storm discharge. The weather was clear and it had not rained for the past 24 hours.
Total
flow was approximately 570,000 to
608,000 gallons at a flow rate of 3000 to 3200 gpm over a time period
of 3 hrs.
15 min. The amount of dye injected was sufficient for a strong visual
observation at 1 ppm for 126,000 gallons to a weak visual of 100 ppb
for 1.26
million gallons.
SFPUC biologists monitored the shoreline from a boat in the open water near the shoreline beyond the tule growth that occurs along the lake edge. No dye was observed in the open water during the 3 hr and 15 min test.
The
dye test indicates that there is no obvious short-circuiting of water
flows in
the system and retention rates should be sufficient for a short term
test. Dye was observed in the band of
tules
between the shoreline and the open water.
However, no dye was observed in the open water indicating the
absence of
any obvious short circuiting within the wetlands at a flow of 3000 gpm
over
3.25 hours.
Pumping
started at
10:00 am. Dye was injected at 10:10 am., using 12 oz of 20% Rhodamine
WT in a
single slug injection. 12 oz. is
sufficient for visible observation of 187,500 gal at 100 ppb. No visual dye observations on the bank side
of the tule buffer by 10:45 am. Daly
City crews used 1500 Dye capsules. The
rate was 500 tablets per 100,000 gal., therefore a half hour interval
was used
for dye injection First tablets were
placed at 10:40. Tablets were placed in cheesecloth bags, and suspended
in the
pipe at the mixing area where the trash pump outlet hoses were inserted. The tablets dissolve completely in six to
nine minutes. 500 tablets will provide
a strong visual (1 ppm) for 127,000 gallons of water.
1500 tablets result in 340 grams of rhodamine WT active
ingredient input into the lake. Visual
observation made at 11:15 revealed the dye plume had reached the tule
buffer
from the shore side, but no visual dye observations were made from the
open
water side of the tules. Observations
were being made on a continuous basis, traversing the length of the
study area
and penetrating into the tules. The final bundle of 500 dye tablets
were placed
in the pipe at 11:45 am. The final
12
oz of liquid dye were poured in at 12:20 resulting a total of 476 gm of
rhodamine
wt active ingredient released into the treatment area.
Final observations at 1:10 pm on the shore
side of the tules showed visual evidence of the dye within the
treatment area. However, no dye was
observed in the open
water. At that time, Daly City personnel noticed the visual plume that
had
migrated to the trash pump intakes, perhaps as a result of flow induced
by the
pumpage. Pumping stopped at 1:15
pm.